Construction of the western arc of the Sofia Ring Road goes on time and expected 3- kilometer stretch to be commissioned in July this year. The abnormally warm weather makes it possible for work to be finished ahead of schedule.

srr

„Over 10 000 vehicles a day will be able to pass along,” said Stefan Chaikov, Chairman of the Board of the “Road Infrastructure” Agency . He and the Minister of Regional Development Desislava Terzieva inspected the construction work.

The constructed plot contains three major facilities – junction with Boulevard “Queen Joanna”, which includes an 18 hole trays, junction at “Slivnitsa” trestle with a 12 mesh and bridge at River Kakach.

„The road junction at „Slivnitsa” is designed on three levels. The construction will ensure conflict-free passing. The ramp will improve transport services for international and domestic traffic and increase safety and security when traveling” said eng. Chaikov.

 

The first level is below the level of the existing intersection. On it will be implemented through traffic in Sofia ring road north-south direction. The second level is at ground level and will be a roundabout with two arched bridge over SEN. The third level is a trestle above the current intersection. The transit flow between “Slivnitsa” and checkpoint “KALOTINA.” Will go through it.Строителството на Западната дъга на софийския околовръстен път околовръстен върви в срок, а необичайно топлото време позволява дори предсрочно приключване.